Home > References > Food
Project One : Food factory freezer monitoring

Background of the project


For existing freezer rooms, customers need a new 24/7 monitoring system. A variety of different machines need to be remotely controlled by the operator.

Solution


Installing a new SCADA system has the following main features:
- The system is running around the clock
- The new HMI screen is set up using Omron NS
- Operators can operate freezer equipment on the HMI (evaporation condenser, petroleum system, etc.)
- Source: Omron PLC-s and Schneider Power Meter

- When the threshold is overwritten, an automatic alarm is generated and upgraded to the relevant person in charge


Conclusion


The main criterion for monitoring systems is a reliable, trouble-free operation. It has been confirmed by the customer that the system has been running without unexpected failures.